Riverside Avenue Watermain Replacement

If you can believe it, the existing water infrastructure on Riverside Avenue is over 50 years old!

Project Overview

  • The District of Sicamous is replacing the aging watermain line from 6" to 10". This will increase fire flow from Kappel Street to Martin Street.
  • Following the water main replacement and upgrade, the roadway will be reconstructed and the sidewalk on the west side will be repaved.
  • This project is funded by capital reserves and development cost charge contributions.

District of Sicamous Council identifies the maintenance and expansion of infrastructure as a strategic priority within the 2022 - 2026 period.

The project is anticipated to begin during the third week of August and reach completion by early October.

UPDATE:

  • The project started on August 20, 2024.
  • The contractor expects the projects to last six weeks.

While upgrades to the Riverside Avenue watermain are underway, traffic will be interrupted. The District of Sicamous is working with the contractor to approve a traffic plan with alternate routes for motorists and pedestrians.

UPDATE:

An alternate route is open to motorists while construction progresses.